RV CLOSED technical Center Room 239 Renovation
Wednesday, August 24, 2011
Tuesday, August 23, 2011
Progress Update
The furniture has been installed
The cabling is completed and tested.
The workstations have been installed.
The tasked have been completed.
The cabling is completed and tested.
The workstations have been installed.
The tasked have been completed.
Friday, August 5, 2011
Progress Update
The furniture scheduled to be delivered by beginning of August.
Cabling, facilities, and client are working to coordinate installation of equipment.
Cabling, facilities, and client are working to coordinate installation of equipment.
Tuesday, July 26, 2011
Progress Update
The furniture scheduled to be delivered by the end of July.
Cabling, facilities, and client are working to coordinate installation of equipment.
Cabling, facilities, and client are working to coordinate installation of equipment.
Monday, July 11, 2011
Progress Update
Cabling, facilities, and client are working to coordinate installation of equipment.
A new cabling quote has been completed.
Furniture is being ordered for the room.
A new cabling quote has been completed.
Furniture is being ordered for the room.
Tuesday, June 14, 2011
Progress Update
Reviewed analysis with client and IT team.
Reviewed furniture design with facilities.
Prepared schematic drawings with drop locations and layout.
The cabling quote is completed and sent forward to facilities.
Another client and team meeting is scheduled for June 10th due to a design change in furniture.
Meeting for coordinating work to be performed by cabling, facilities, and INtech.
Reviewed furniture design with facilities.
Prepared schematic drawings with drop locations and layout.
The cabling quote is completed and sent forward to facilities.
Another client and team meeting is scheduled for June 10th due to a design change in furniture.
Meeting for coordinating work to be performed by cabling, facilities, and INtech.
Friday, May 27, 2011
Project Activities
Met with facilities project management to review furniture design.
Met with client and IT team to review the analysis.
The cabling quote has been forward to facilities and IT team members.
Meet with voice group and there is no change for the phone.
Update communication log, Mariner, and blog.
Follow up with facilities on the furniture design and a timeline for work to start.
Have the cabling vendor prepare another quote since some the design has changed.
Met with client and IT team to review the analysis.
The cabling quote has been forward to facilities and IT team members.
Meet with voice group and there is no change for the phone.
Update communication log, Mariner, and blog.
Follow up with facilities on the furniture design and a timeline for work to start.
Have the cabling vendor prepare another quote since some the design has changed.